Can you explain this? Can’t seem to crack it

Answered

Andrew can finish making a pizza in ‘x’ hours working at a constant rate. Barry can finish a pizza in ‘y’ hours working at a constant rate. If Andrew works for ‘z’ hours and is then joined by Barry until 50 pizzas are finished, for how long will Barry and Andrew operate simultaneously?

 

  1. (50xy-z)/(x+y)
  2. y(50x-z)/(x+y)
  3. 50y(x-z)/(x+y)
  4. (x+y)/(50xy-z)
  5. (x+y-z)/(50xy)
Intermediate Asked on January 19, 2017 in Problem Solving.
Add Comment
1 Answer(s)
Best answer

Hi Chaitanya,

This question you can solve using, Plugging In or Normal approach,

It’s very important for these types of questions to follow a step by step approach.

Let’s draw the rate chart here,

Work = Rate * Time
Person Work time Rate
Andrew 1 x 1/x
Barry 1 y 1/y

 

If Andrew for “z” hours then he would complete (z/x) no. of pizzas.

Total work is to complete 50 pizzas,

Since Andrew would have completed (z/x) number of pizzas,

Then the remaining pizzas would 50-(z/x) = (50x-z)/x

No Barry also working along with Andrew to complete the remaining pizza,

We should find the time taken for them to complete this,

Time taken = Work/rate

= ((50x-z)/x)/ (1/x+1/y)

= ((50x-z)/x)/(x+y/xy)

= ((50x-z)y)/(x+y)

So the answer is B.

We can also do plugging-in

Let us say x = 10, y = 50

Given, Andrew can make 1/10 pizza every hour

Barry can make 1/50 pizza every hour

Let us say z = 100.

Now Andrew has already made 10 pizzas and 40 pizzas are left which are to be made by both Andrew and Barry. They together will operate for 40/(1/10 + 1/50) hours, which is equal to 1000/3. The values match with our answer option:

y (50x – z)/(x+y) = 50(500 – 100)/(60) = 50(400)/(60) = 1000/3.

So the answer is B.

Hope it is clear.

Expert Answered on January 19, 2017.
Add Comment

Your Answer

By posting your answer, you agree to the privacy policy and terms of service.